Stated capacity is a ceiling
Announced and permitted MW usually describe the whole campus at full build. Power draw for the first years is far lower.
Estimates are size classes
An estimate from floor area or acreage can span a factor of two or more. Use it to sort and compare, not to quote.
County-only locations
When a campus is only placed at the county center, the map draws it dim, and the record leaves out distances and anything measured at the pin. Water stress for such a campus describes the county center, not the site. See Location accuracy.
Totals cover the default Pipeline
Home and Pipeline totals count the default Pipeline only. Operating and Unconfirmed campuses are separate, and so are figures that only third-party lists give.
Dates mean different things
| Date | What it is |
|---|---|
| Stage date | The date of the record that set the current stage |
| Latest record | The newest dated record on the campus |
| Change date | The record’s own date, not the day we found it |
| Data as of | The date of the data release |
A filing we find late shows under its own date, so it can land below older entries in Changes.
Opposition is matched by name
Petitions and posts are linked to a campus by place and project names in their text. Read the item before counting it. See Opposition matches.
Jobs are near, not at
Job postings are matched to the city around a campus. They are leads, not proof the job belongs to that campus.
Some settings live in your browser
Column choices, the map base layer and Ask history stay in the browser you set them in.