Docs / How we calculate
Electricity and power bill
Operators rarely publish how much power a campus will draw in a year, so we estimate it from capacity and show a range
The formula
Low and high end
A campus never runs at its full rated capacity all year. The low end assumes 55% of capacity in use on average, the high end 80%. Where an operator has published a figure for the site, we print that and no range.
Capacity here is facility capacity: the power the campus can draw from the grid, cooling included. When capacity is itself a range, the low end uses the low capacity and the high end uses the high capacity. Capacity estimates explains where capacity comes from.
Power bill
Electricity each year multiplied by the industrial rate of the utility that serves the site.
The rate is the energy rate in the utility’s filed industrial or commercial tariff. When we cannot match a tariff, or the matched rate falls outside 2.0 to 45.0 ¢/kWh, we use the state’s average industrial rate instead. The bill covers energy only. Demand charges, transmission riders and negotiated contracts are not in it, so a real bill for a large campus can differ a good deal.
When an operator has published the site’s annual electricity use, the bill uses that figure at the same rate, and the range collapses to one value.
| Input | This campus | Where it comes from |
|---|---|---|
| Electricity each year | 48 to 70 TWh4.8 to 7.0 TWh482 to 701 GWh | The formula above |
| Industrial rate | 3.72 ¢/kWh3.72 ¢/kWh3.72 ¢/kWh | The utility's filed tariff |
| Power bill each year | $1.8 to $2.6 billion$179 to $261 million$18 to $26 million |
When we show nothing
- No capacity on record and nothing to estimate it from
- No utility matched to the site, so no bill