Docs / How we calculate
Build phase from aerials
How we read the build phase of a site from aerial imagery and when a site is ahead of its record
What we look at
A square of aerial imagery about 340 m to 400 m across, centred on the campus pin, at about 0.6 m per pixel. A vision model labels what it sees and how sure it is: high, medium or low.
Phases
| Phase | What it means |
|---|---|
| Undeveloped | Field, forest or open land |
| Active grading or pad | Earthwork, cleared and levelled ground |
| Shell under construction | Building frames or walls going up |
| Completed campus | Finished data center buildings |
| Substation only | A substation and little else |
| Non-DC parcel | Homes, retail or other buildings that are not a data center |
| Unclear | The model could not tell |
Ahead of the record
A campus is ahead of the record when the image shows grading, a shell or a completed building with high confidence, while its record still says Announced or a zoning stage. Earthwork often starts before the permit we can see.
Roof area and data halls
When the model finds roofs, we add up roof outlines of 800 m² or more. Roof area also feeds Capacity estimates when nothing better exists.
Compare
The Compare slider on a record shows the site in different years. Use the year buttons, or the arrow, Home and End keys.
When we show nothing
- No aerial image covers the pin yet
- The location is only known to the county, so there is no site to look at