# Build phase from aerials

How we read the build phase of a site from aerial imagery and when a site is ahead of its record.

Source: https://docs.wattlas.io/methods/build-phase-from-aerials/

## What we look at

A square of aerial imagery about 340 m to 400 m across, centred on the campus pin, at about 0.6 m per pixel. A vision model labels what it sees and how sure it is: high, medium or low.

## Phases

| Phase | What it means |
| --- | --- |
| Undeveloped | Field, forest or open land |
| Active grading or pad | Earthwork, cleared and levelled ground |
| Shell under construction | Building frames or walls going up |
| Completed campus | Finished data center buildings |
| Substation only | A substation and little else |
| Non-DC parcel | Homes, retail or other buildings that are not a data center |
| Unclear | The model could not tell |

## Ahead of the record

A campus is ahead of the record when the image shows grading, a shell or a completed building with high confidence, while its record still says Announced or a zoning stage. Earthwork often starts before the permit we can see.

## Roof area and data halls

When the model finds roofs, we add up roof outlines of 800 m² or more. Roof area also feeds [Capacity estimates](/methods/capacity-estimates/) when nothing better exists.

## Compare

The Compare slider on a record shows the site in different years. Use the year buttons, or the arrow, Home and End keys.

## When we show nothing

- No aerial image covers the pin yet
- The location is only known to the county, so there is no site to look at

## What to watch for

The phase is a model's reading of one image, with a confidence. Built-out percent is the model's guess, not a measurement.