# Electricity and power bill

Operators rarely publish how much power a campus will draw in a year, so we estimate it from capacity and show a range.

Source: https://docs.wattlas.io/methods/electricity-and-power-bill/

## The formula

Capacity × Hours in a year × Share in use = Electricity each year

| Example | Capacity | Hours in a year | Share in use | Electricity each year |
| --- | --- | --- | --- | --- |
| 10,000 MW campus | 10,000 MW | 8,760 h | 55 to 80% | 48 to 70 TWh |
| 1,000 MW campus | 1,000 MW | 8,760 h | 55 to 80% | 4.8 to 7.0 TWh |
| 100 MW campus | 100 MW | 8,760 h | 55 to 80% | 482 to 701 GWh |

## Low and high end

A campus never runs at its full rated capacity all year. The low end assumes 55% of capacity in use on average, the high end 80%. Where an operator has published a figure for the site, we print that and no range.

Capacity here is facility capacity: the power the campus can draw from the grid, cooling included. When capacity is itself a range, the low end uses the low capacity and the high end uses the high capacity. [Capacity estimates](/methods/capacity-estimates/) explains where capacity comes from.

## Power bill

Electricity each year multiplied by the industrial rate of the utility that serves the site.

The rate is the energy rate in the utility's filed industrial or commercial tariff. When we cannot match a tariff, or the matched rate falls outside 2.0 to 45.0 ¢/kWh, we use the state's average industrial rate instead. The bill covers energy only. Demand charges, transmission riders and negotiated contracts are not in it, so a real bill for a large campus can differ a good deal.

When an operator has published the site's annual electricity use, the bill uses that figure at the same rate, and the range collapses to one value.

| Input | 10,000 MW campus | 1,000 MW campus | 100 MW campus | Where it comes from |
| --- | --- | --- | --- | --- |
| Electricity each year | 48 to 70 TWh | 4.8 to 7.0 TWh | 482 to 701 GWh | The formula above |
| Industrial rate | 3.72 ¢/kWh | 3.72 ¢/kWh | 3.72 ¢/kWh | The utility's filed tariff |
| Power bill each year | $1.8 to $2.6 billion | $179 to $261 million | $18 to $26 million |  |

## When we show nothing

- No capacity on record and nothing to estimate it from
- No utility matched to the site, so no bill

## What to watch for

Stated capacity is often the full build-out, years away. A campus at the Announced stage will draw far less than this for a long time.