# Pipeline, Operating, Unconfirmed

The three groups every campus falls into and the test for the default Pipeline view.

Source: https://docs.wattlas.io/methods/pipeline-operating-unconfirmed/

## Pipeline

Planned and under construction campuses in the US with an official record of their stage, from Announced through Construction. Leads and sites flagged as not a data center are left out.

The default Pipeline view also needs the campus to be open and solid:

- **Open** means not withdrawn or denied
- **Solid** means it has a capacity figure, an owner, data center wording or an official source, and evidence from 2021 or later, or it is under construction

Show all drops the solid test. Stage set to Withdrawn shows campuses that were cancelled.

## Operating

Campuses already running, with a state, that are not flagged as something other than a data center. An operating site found only in a directory lands here, not in Unconfirmed.

## Unconfirmed

Campuses that only appear in third-party lists, with a state, that are not operating. No official record proves their stage yet. A lead moves into Pipeline once a primary record is found.

## Which one counts in totals

Home and Pipeline totals use the default Pipeline view. Operating and Unconfirmed have their own counts.

## What to watch for

Show all in Pipeline drops the evidence test, so it includes campuses with old or thin records. Totals change when you switch it.