# Grid around the site

How we measure the substations, lines, new generation and nearby campuses shown in a record's Power section.

Source: https://docs.wattlas.io/methods/grid-around-the-site/

## Nearest infrastructure

| Item | How we find it |
| --- | --- |
| Nearest substation | Where named lines of 115 kV or more end, grouped within about 2 km |
| Nearest line of 230 kV or more | Straight-line distance to the closest point on the line |
| Nearest gas pipeline | Straight-line distance to the closest point on the pipeline |

Distances are in km to two decimals, measured from the campus pin. We show them only when the location is an exact or likely site. See [Location accuracy](/methods/location-accuracy/).

## Grid operator and balancing authority

The grid operator is shown by region: PJM, ERCOT, MISO, SPP, CAISO, NYISO or ISO-NE, or Non-ISO where a utility runs its own area. The balancing authority is the main one for the state, not one matched to the exact site. Peak, clean and gas shares come from that area's hourly generation.

## County queue

New generation waiting to connect to the grid in the campus's county, in MW. We split it in two:

- **Firm or with storage** (dispatchable in the API): gas, nuclear, storage, hydro, coal, geothermal and hybrid plants (including solar or wind paired with battery storage)
- **Wind and solar alone**

The queue is supply, not demand. It lists plants asking to connect, not data centers, and it does not show signed agreements. Many plants in a queue are never built.

## Power around the site

- Planned and retiring generation within 25 km, as nameplate MW
- Nuclear plants within 50 km
- Other operating campuses within 10 km, from our own records
- The nearest moratorium in force within 25 km in the same state

## Industrial price

The industrial price band on Home and on a record is the 10th percentile, median and 90th percentile of state industrial rates in ¢/kWh across confirmed campuses. Year on year change is at state level.

## When we show nothing

- Distances to substations, lines and pipelines when the location is only known to the county
- Distances over 300 km, which say more about missing data than about the site

## What to watch for

The county queue counts generation waiting to connect, which is supply. It does not tell you a campus has a grid connection, a signed agreement or any power reserved for it.